How long do I have? Time limits in the scheme

Help & AdviceReading time approx 4 min

The scheme has two main clocks: one for starting your works and one for finishing them and claiming your final payment. Missing a deadline can cost you your grant, so it helps to know which is which.

These limits are set by Section 19 of the Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks Act 2022, the law behind the Enhanced Scheme. Some were changed in 2026.

The time limits at a glance

  • Starting works: 78 weeks (about 18 months) from the date you are notified of your remediation option grant.
  • Finishing works and claiming your final payment: 130 weeks from the date you start works. This was 65 weeks until 2026.
  • Extension: up to 24 weeks more on either period, in exceptional circumstances.
  • Asking for an extension: more than 2 weeks before the period runs out. This was 12 weeks until 2026.
  • Appealing a decision: 90 days from being notified.

How long do I have to start works?

You must start your approved works, for example demolition, within 78 weeks of the date of your Notification of Remediation Option Grant. If you do not, you risk losing the grant.

The clock starts when you receive your formal notification from your council or the Housing Agency.

How long do I have to finish and claim?

Once you have started, you must finish your works and submit your application for final grant payment within a set period.

The Act originally set this at 65 weeks from the start of works. The Dwellings Damaged by Use of Defective Concrete Blocks (Increased Grant) Regulations 2026 extended it to 130 weeks. This change came with the Amendment Act 2025.

Can I get more time?

Yes, in some cases. Under Section 19(3) of the Act, you can ask for an extension to either period: the time to start, or the time to finish and claim.

  • An extension is possible where there is a delay due to exceptional circumstances beyond your control, despite you acting with all due diligence.
  • Each extension can be for no more than 24 weeks.
  • You must ask more than 2 weeks before the period you want extended runs out. This was more than 12 weeks until the 2026 Regulations. Section 19(4)(b) of the Act gives more detail.

In Donegal you can apply through the Online Portal by choosing "Apply for Extension of Time". To extend the time to start, this is an Extension of Period for Commencement of Works.

What happens if I do not start in time?

If you do not start works within 78 weeks of your grant being confirmed, or within 102 weeks if you were given the 24-week extension, you are treated as having withdrawn from the scheme.

Can I reapply?

Yes, you can reapply later. If you do, Donegal County Council will ask why works did not start within the 78-week or 102-week period, and may ask for documents to support your case. The council will decide whether your reasons are reasonable and whether the reapplication is valid.

What if I was waiting for a technical review?

In simple terms, Donegal County Council will let you start works after the 78 weeks have passed if the reason you did not start was that you were waiting for a technical review.

How long do I have to appeal?

If you want to appeal a decision on your application, including a decision on the increased grant, you have 90 days from the date you are notified. See appeals and applying for the increased grant.

You may hear other figures

Some guidance circulating about the scheme mentions:

  • a 65-week "critical review" point, used to track progress on Option 1 (demolish and rebuild) projects, with homeowners who are well behind facing extra questions before final stage payments
  • extensions being granted more easily, or automatically, for "force majeure" events such as labour shortages or severe weather
  • an effective 104-week (2-year) window for complex rebuilds where a contractor is on site and active
  • extensions in 6-month steps where your contractor provides a revised Schedule of Works

These points are not set out in the Act or in the Department's 2026 guidance. Under the Act the 65-week limit was a legal deadline for claiming final payment, and it is now 130 weeks. Do not rely on any of these without checking with your local authority first.

Who should I ask?

Deadlines depend on the dates on your own letters. Check them with your engineer and your local authority, and ask early if you think you may need more time. You can also contact us.

Sources

  1. Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks Act 2022 (opens in a new tab)Irish Statute Book · irishstatutebook.ie
  2. Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks (Amendment) Bill 2025 (opens in a new tab)Houses of the Oireachtas · oireachtas.ie
Still need help? Call the party office on 074 913 0207Ask a question